Summary
- Modernization of EAF #1 completed
- Revamp of EAF #2 in September 2024
Key technologies involved in the revamp project, such as electric arc furnace EDGE design, Condoor automatic slag door, SafEBT solution and a set of auxiliary devices, have been instrumental in optimizing processes and production efficiencies.
The full completion of the project is scheduled for September 2024 with the start-up of EAF #2.
SMS Group looks forward to continuing its relationship with Nucor Steel Utah as they work towards further advancements in steel production.